Thanks to Prof. Chen-Ching Liu
and Ph.D. Candidate Madeleine Gibescu of the University of Washington for this problem
set.
Download the cases needed for the Assignment
(PW Simulator 5.0 or
later format)
A one line diagram, together with the bus and line data, of a 5-bus
power system is shown below; the system will be referred to as utility A. Solve the
following problems using the PowerWorld Simulator and the original data file 454_0.pwb and the
one-line diagram file 454_0.pwd.
For the power system of utility A, use the PowerWorld program to find
the MVAr rating of a shunt capacitor at bus 3 that increases V3 to 1.00
p.u.
Determine the effect of the capacitor bank on the line loading and total I2R
losses.
Run the original power flow for utility A. Do you find any voltage
violations? (The normal range of bus voltages is assumed to be 0.95-1.05
p.u.) Now suppose
both transformers in this system are tap changing transformers whose taps can be varied
from 0.85 to 1.15 p.u. in increments of 0.05 p.u. Determine the tap settings required to
increase the voltage at bus 3 to 0.95 p.u., while causing as few high voltage violations
as possible at the other buses.
A new transformer is installed between buses 2 and 5, in parallel with
the existing transformer between buses 2 and 5. The new transformer is identical to the
existing transformer. The taps on both transformers are set to the nominal value, 1.0
p.u.
Find the real power, reactive power and MVA supplied by each of these transformers to bus
5.
Refer to the one-line diagram of utility A. Suppose an additional line
is installed between buses 3 and 4. The line parameters of the added line are equal to
those of the existing line 3-4. Determine the effects on the voltage at bus 3, line
loading and total I2R losses.
In problem 2 you already ran the power flow for utility A and detected
low voltage violations. Place a capacitor at bus 3 to bring the bus 3 voltage up to 0.95
p.u. Determine the size of the capacitor bank. Now suppose the line between buses 3 and 5
is removed for maintenance. Run the power flow again. Is the operating condition
acceptable? If not, determine the amount of load you have to shed at bus 3 in order to
maintain the bus 3 voltage above 0.95 p.u. Cut the same percentage of MW and MVAr at bus
3.

Initial Bus Records
Bus PU Volt Volt (kV) Angle (Deg) Load
MW Load MVR Gen MW Gen MVR
1 1.05000 15.75 -0.500
80.00 40.00 520.00
238.94
2 1.00000 15.00 0.000
390.70 26.16
3 0.87580 302.15 -21.256
800.00 280.00
4 1.02871 354.90 -2.755
5 0.99196 342.23 -4.495
Line Records (Base MVA = 400)
From To Xfrmr R
X B
MVA Lim
4 1 Yes 0.00300 0.04000 0.00 1000.0
2 5 Yes 0.00600 0.08000 0.00 600.0
4 3 No 0.03600 0.40000 0.44 1200.0
5 3 No 0.01800 0.20000 0.44 1200.0
4 5 No 0.00900 0.10000 0.22 1200.0